Data center under construction, Ridgeville, South Carolina.
Photo: J. Henry Fair. Flight thanks to Southwings.
The facts
Growth needs public scrutiny
Data centers support the digital services we use every day. Their locations, electricity contracts, cooling systems, and public incentives deserve careful review. We are building a source-linked record of South Carolina projects and their effects on communities.
Electricity demand and utility bills
Large new electricity loads can require investment in generation, transmission, and distribution. The key question is who pays when infrastructure is built, a project changes, or a customer leaves. We support full cost responsibility, long-term minimum contracts, exit fees, and financial assurances.
S.784 and H.5215 proposed protections against shifting large-load costs to other customers. These were proposals, not enacted protections.
Dominion’s January 2026 request sought about $322 million in additional annual revenue, with a proposed residential bill increase of about 12.7%. A subsequent settlement reduced the typical residential increase to 7.62%, or just under $12 a month at 1,000 kWh. The PSC approved the settlement in June 2026. Duke Energy Carolinas’ approved residential increase of 4.3% took effect August 1, 2026. These are utility rate-case changes, not a calculation of costs caused only by data centers. Dominion settlement and bill impacts · PSC approval directive · Duke Energy Carolinas.
Water consumption
Water use depends on cooling technology, climate, facility load, and how water consumption is measured. A single daily-use figure should not be applied to every 100 MW facility. We want recirculating cooling, reclaimed water where feasible, and review of cumulative withdrawals from each river basin and aquifer.
York County describes QTS's planned closed-loop cooling approach. Read the county's information. Company and county claims should be distinguished from measured operating data.
The Lawrence Berkeley National Laboratory report distinguishes water consumed directly for cooling from water used to generate electricity. Cooling systems and local conditions vary, so there is no single daily-use figure for a typical large facility. The report estimates that U.S. data centers directly consumed about 66 billion liters of water in 2023, roughly 17.4 billion gallons. This is a national modeled estimate, not a measurement of South Carolina facilities. LBNL’s 2024 report · EPA WaterSense.
More data centers means more gas, coal, and diesel
New electricity demand can reach far beyond a data center’s fence. Our concern is that it can drive new methane gas plants and pipelines or delay coal retirements. We want new large data centers to bring new clean energy and storage onto the grid.
South Carolina regulators approved the proposed 2,200 MW Canadys gas plant in May 2026. Santee Cooper’s proposed September 2026 resource plan also includes another gas combined-cycle unit for 2035 to serve load growth and support future coal retirements. These are systemwide plans, not a measure of demand attributable only to data centers. Canadys approval · 2026 resource plan.


New pipelines
New gas generation can require new pipelines. Pipeline routes deserve public scrutiny for their effects on private land, rivers, wetlands, and sensitive habitat, including the ACE Basin. For federally certificated interstate gas pipelines, companies can seek easements through eminent domain when negotiations fail. Specific routes and approvals must be checked project by project. FERC’s landowner guide.
Dirty air
Gas combustion still releases air pollution. EPA identifies nitrogen oxides, volatile organic compounds, and other pollutants from gas engines and turbines. Fine-particle pollution is linked to asthma attacks, heart attacks, hospital visits, and premature death. Children, older adults, and people with heart or lung disease face greater risks. The effects of a particular plant depend on its equipment, controls, emissions, and nearby exposure. EPA: engine exhaust · EPA: particle pollution and health.
Methane leaks
Over 20 years, methane has about 80 times the warming potential of carbon dioxide. Leaks across gas production and delivery add to the climate impact of burning gas. Long-lived infrastructure requires scrutiny of both combustion emissions and methane leakage. UN Environment Programme: methane facts.
Diesel backup generators
Data centers can use banks of diesel generators for backup power. Testing and outages can add pollution near surrounding neighborhoods. Diesel exhaust contains nitrogen oxides, fine particles, and other pollutants, and can worsen asthma and heart and lung disease. Ask for generator numbers, engine standards, operating limits, testing schedules, and air-permit records. EPA: diesel exhaust and health.
Big tax breaks, few permanent jobs
Large capital investments and permanent job totals are different measures. Public evaluation should show both, along with incentives, infrastructure commitments, and enforceable obligations.
| Project | Announced or committed investment | Planned operational jobs |
|---|---|---|
| QTS, York County | More than $8 billion, long term | 200 permanent jobs |
| Meta, Aiken County | More than $800 million | Approximately 100 once completed |
Sources: York County and Meta. Construction jobs are separate from operational employment.
- Sales and use tax exemption: S.C. Code §12-36-2120(79) covers qualifying computer equipment, software, and specified electricity use. The investment threshold is at least $50 million over five years for one taxpayer, or $75 million collectively for two or more taxpayers. Job, wage, certification, and other conditions also apply. Read the statute.
- County property-tax deals: Fee-in-lieu-of-tax agreements can reduce an assessment ratio from 10.5% to 6%; some qualifying large investments can receive a 4% ratio. Terms depend on the agreement. SCDOR says a single piece of property can remain covered for up to 40 years with county consent, depending on the agreement. SCDOR: fee in lieu of taxes.
- Disclosure: Good Jobs First’s April 2026 report named South Carolina among 14 states failing to disclose data center tax-abatement revenue losses. Its later 2026 report says South Carolina subsequently made its first disclosure. We support complete, ongoing public reporting. April finding · Later update.
Sumter County update: October 27, 2026
South Carolina Record reports final approval of data center standards (OA-26-01) and second-reading approval of the moratorium rescission (26-1056). The moratorium remains in effect pending a third and final rescission vote. The standards concern unincorporated Sumter County.
SC Data Center Watch supports meaningful, enforceable protections. Our review priorities are water and cooling requirements, utility costs, noise, setbacks, independent technical assessments, and enforcement. Adoption alone does not establish that these protections are adequate.
The county’s official records page lists the October 27 agenda, but minutes and the final adopted text have not been reviewed. The meeting summary is AI-assisted, not an official record. Open Sumter’s map entry for sources and next steps.
Policies in other states
Florida and Oregon came to the same conclusion: data centers should pay their own way.
Florida: SB 484, 2026
Florida’s law requires large-load tariffs designed to make covered customers pay their own cost of service and protect other ratepayers from nonpayment risk. The enrolled text defines covered large loads at 50 MW or more. It preserves local land-use authority and creates distinct water-permitting requirements. The Senate records it as Chapter 2026-65. Bill history · Official summary.
Oregon: POWER Act, 2025
HB3546 creates a separate service classification for covered large energy-use facilities and seeks to prevent unwarranted cost shifting. Covered electricity-service contracts must last at least 10 years and include minimum-payment obligations. Read the enrolled act.
Virginia: site assessments and reporting
Virginia’s 2026 code requires sound-profile site assessments before specified zoning approvals for new facilities expected to need at least 100 MW. Localities may also require assessment of water, agricultural resources, parks, historic sites, and forestland. A separate state report collects information about electricity agreements, water use, and generator permits. Site-assessment law · October 2026 report.
California: water, electricity, and local information
In September 2026, California enacted a package of data center laws addressing reporting, water-use disclosures, electricity costs, and local land-use review. The measures are a useful comparison for South Carolina; their individual requirements and effective dates differ. Governor’s announcement and bill list.
Pennsylvania: a water-study proposal
SB1459 would require proposed data centers to conduct water-use studies. The official history records referral to the Senate Environmental Resources and Energy Committee on September 24, 2026. This is a proposal, not an enacted requirement. Bill and status.
New York: a temporary statewide pause
On July 14, 2026, the governor announced an executive order pausing specified state environmental permits for new hyperscale data centers for up to one year while the state develops an environmental review framework. It does not amount to a permanent ban or cancellation of every existing approval. Executive-order announcement.
Tucson, Arizona: local review and standards
Tucson declined to move forward with the proposed Project Blue arrangement in August 2025. Following a public process, the city adopted large-scale data center regulations in August 2026, effective September 4. They include public review, separation distances, noise studies, environmental review, and adequate water and power supply. City record and regulations.
Douglas County, Georgia: a rezoning denial
Local reporting in July 2026 describes a 4–1 county commission vote denying rezoning for a proposed data center campus near Interstate 20. This is a project-specific local decision. Local report.
Why facility counts differ
Data Center Map listed 55 directory entries across 12 South Carolina markets when checked October 25, 2026. That directory count is not the same as a count of operating hyperscale campuses. Cleanview’s October page lists operating and planned buildings, but its displayed totals do not reconcile: 13 operating plus 24 planned equals 37, while its headline says 38. Its capacity subtotals also differ from its stated total. We therefore do not use those totals as campaign statistics. Data Center Map · Cleanview.
The map below includes project records, including grouped buildings, campuses, and canceled or withdrawn proposals. It is a documented project tracker, not a statewide facility census.
SC Data Center Watch · County research map
Data centers and local action in South Carolina
Explore the projects and local decisions in our research tracker. Select a county to see project status, ordinances, source links, and questions still being checked.
County shading shows where records are available. It does not mark facility parcels or the boundaries of a moratorium. A town’s rules do not apply to its entire county.
Start with a county.
Records mix buildings, campuses, and proposals. These totals are not a count of South Carolina facilities.
Expand each entry for status, dates, permitting notes, and its source. Uncertain details remain identified.
Abbeville County
0 project records · 0 local action records
No entry in the supplied tracker. This does not establish that the county has no data centers or local rules.
Aiken County
2 project records · 0 local action records
Projects
Meta Aiken – Building 1
Under construction
- Developer / Operator
- Meta
- Municipality (if any)
- Not confirmed — Aiken County press materials don't specify incorporated city limits
- Capacity / Investment
- 109 MW; part of $800M total Aiken investment, 100 operational jobs
- Expected Year / Milestone
- 2027
- Permitting & Process Notes
- 715,000 sq ft facility; Meta's first SC data center, selected Aug. 2024.
Meta Aiken – Building 2
Planned
- Developer / Operator
- Meta
- Municipality (if any)
- Not confirmed — see note on Building 1
- Capacity / Investment
- 91 MW
- Expected Year / Milestone
- 2027
- Permitting & Process Notes
- Second building of the Aiken campus.
Allendale County
0 project records · 0 local action records
No entry in the supplied tracker. This does not establish that the county has no data centers or local rules.
Anderson County
0 project records · 0 local action records
No entry in the supplied tracker. This does not establish that the county has no data centers or local rules.
Bamberg County
0 project records · 0 local action records
No entry in the supplied tracker. This does not establish that the county has no data centers or local rules.
Barnwell County
0 project records · 0 local action records
No entry in the supplied tracker. This does not establish that the county has no data centers or local rules.
Beaufort County
0 project records · 0 local action records
No entry in the supplied tracker. This does not establish that the county has no data centers or local rules.
Berkeley County
3 project records · 0 local action records
Projects
Google Moncks Corner – Buildings 1,2,3,4,5,6,8,9 (no Bldg 7 in tracker)
Operating (2008-2022)
- Developer / Operator
- Municipality (if any)
- Moncks Corner
- Capacity / Investment
- 435 MW combined (8 buildings); largest single building (Bldg 4) is 121 MW
- Expected Year / Milestone
- Bldg 1: 2008; Bldg 9: 2022
- Permitting & Process Notes
- Long-operating flagship SC campus; anchors state's argument that large data centers are commercially viable under high standards. NOTE: tracker skips a Building 7 — not clear if it was never built, renumbered, or just unreported.
Google Moncks Corner – Building 10
Operating (2026) per Cleanview
- Developer / Operator
- Municipality (if any)
- Moncks Corner
- Capacity / Investment
- 91 MW
- Expected Year / Milestone
- 2026
- Permitting & Process Notes
- Part of Google's announced $9B SC investment plan through 2027. Cleanview lists Building 10 as operating, year 2026 (MW not shown on the free page; 91 MW figure carried from earlier tracker entry).
Google Moncks Corner – Building 11
Planned
- Developer / Operator
- Municipality (if any)
- Moncks Corner
- Capacity / Investment
- 91 MW
- Expected Year / Milestone
- 2028
- Permitting & Process Notes
- Expansion building tied to Google's $9B statewide investment announcement.
Calhoun County
0 project records · 0 local action records
No entry in the supplied tracker. This does not establish that the county has no data centers or local rules.
Charleston County
0 project records · 1 local action records
Local action
Municipal rules apply within that town or city, not across the whole county.
Mount Pleasant (municipal, Charleston County)
PASSED — 2-year moratorium (finalized Oct. 2026)
- Type
- Municipality
- Ordinance / Action
- 2-year moratorium on data-center applications (facilities ≥1 MW)
- Key Date(s)
- Finalized by Town Council; reported 10/14/26 (vote date and tally not stated in coverage). Originally proposed as 120 days; extended to 2 years.
- Summary
- Temporarily halts the town's acceptance, processing and approval of data-center applications, permits and related requests for facilities of 1 MW or more. Town will study suitable locations and conditions and recommend zoning/comprehensive-plan changes; council wants future proposals to go through public approval rather than by-right. Proactive measure — no large-scale proposal is currently before council; Mayor Will Haynie said hyperscale centers "are not going to be coming to Mount Pleasant."
Cherokee County
1 project records · 1 local action records
Projects
Cielo Cherokee County Campus
Planned / early site work
- Developer / Operator
- Cielo Digital Infrastructure
- Municipality (if any)
- Off Ford Road, Gaffney area (~86 acres, per Baxtel) — not confirmed whether inside Gaffney city limits
- Capacity / Investment
- 300 MW; $2.1B; 4 buildings (~400,000 sq ft each) + substation
- Expected Year / Milestone
- Initial operations end of 2028
- Permitting & Process Notes
- Announced June 2025; still listed as planning stage; no newer public update found (10/25/26). Gaffney's municipal ID-2 data-center zoning (Jan. 2026) applies only if the site is within Gaffney city limits — not confirmed.
Local action
Municipal rules apply within that town or city, not across the whole county.
Gaffney (municipal, Cherokee County)
PASSED
- Type
- Municipality
- Ordinance / Action
- New "ID-2" (Industrial District 2) zoning classification
- Key Date(s)
- Adopted unanimously, Jan. 5, 2026
- Summary
- Requires written verification of adequate power/water infrastructure and a noise study by an SC-registered acoustical engineer, with post-construction testing possible, for any data center within Gaffney city limits.
Chester County
0 project records · 1 local action records
Local action
Municipal rules apply within that town or city, not across the whole county.
Chester County
PASSED — 6-month moratorium
- Type
- County
- Ordinance / Action
- 6-month pause on data-center development actions
- Key Date(s)
- 1st reading 6/15/26 (also referenced 6/18/26); council approved unanimously Mon. 7/20/26 (per WBTV)
- Summary
- Six-month pause on data-center development actions. Coverage does not state whether 7/20 was the third/final reading or the exact effective date — confirm with county.
Earlier InfraWatch research
June–July 2026 research, shown for comparison. Later tracker updates above take precedence.
2026-06: Data-center zoning standards + 6-month pause (first reading) — Chester County Council
The CSV export does not preserve the original article links. Confirm the underlying record before relying on this lead.
InfraWatch sources and methodology ↗Chesterfield County
0 project records · 1 local action records
Local action
Municipal rules apply within that town or city, not across the whole county.
Chesterfield County
PASSED
- Type
- County
- Ordinance / Action
- Ordinance 25-26-23 — moratorium
- Key Date(s)
- Adopted 6/1/26 (early June per SC Daily Gazette)
- Summary
- Temporary moratorium in unincorporated areas on zoning approvals, construction permits, site-plan approvals, and other county actions authorizing data centers, data processing facilities, or crypto-mining operations. Runs until Jan. 1, 2028 or until county regulations are adopted, whichever is first.
Earlier InfraWatch research
June–July 2026 research, shown for comparison. Later tracker updates above take precedence.
2026-06: Data-center moratorium (~18 months) — Chesterfield County Council
The CSV export does not preserve the original article links. Confirm the underlying record before relying on this lead.
InfraWatch sources and methodology ↗Clarendon County
0 project records · 0 local action records
No entry in the supplied tracker. This does not establish that the county has no data centers or local rules.
Colleton County
1 project records · 1 local action records
Projects
Colleton County / Cooks Hill Rd Campus (proposed, 9 buildings)
Proposed — site now inside ACE Basin Data Center Exclusion Area (SELC settlement, 10/5/26)
- Developer / Operator
- Eagle Rock Partners / Thomas & Hutton
- Municipality (if any)
- Unincorporated (ACE Basin watershed)
- Capacity / Investment
- 859 acres; ~1,000 MW; 2 substations
- Expected Year / Milestone
- TBD
- Permitting & Process Notes
- Original Eagle Rock complex proposed Dec. 2025 on an ~850-acre parcel at the Ashepoo River headwaters (appears to be this site; coverage doesn't use the name "Cooks Hill Rd"). Sought special exception under Ord. 25-O-10; SELC sued 1/2026. County adopted a 6-month moratorium 7/7/26 (Ord. 26-O-04), then partially repealed it for areas west of I-95 and industrial-zoned land, approved a Digital Infrastructure Overlay District 9/14/26 (unanimous), and on 10/5/26 settled with SELC, creating a Data Center Exclusion Area covering most of Colleton's ACE Basin, including the 850-acre parcel. Whether the project is formally dead is not stated — confirm before citing.
Local action
Municipal rules apply within that town or city, not across the whole county.
Colleton County
PASSED — Zoning (2025), moratorium (2026, since partially repealed), overlay district (9/2026), ACE Basin exclusion area (settlement 10/5/26)
- Type
- County
- Ordinance / Action
- Ordinance 25-O-10 (zoning) + Ordinance 26-O-04 (moratorium)
- Key Date(s)
- 25-O-10: 2025; 26-O-04: adopted unanimously 7/7/26; Digital Infrastructure Overlay District approved unanimously ~9/14/26; SELC settlement 10/5/26
- Summary
- 25-O-10 made data centers special-exception uses in RD-1/RD-2/light industrial and conditional uses in industrial/heavy industrial; SELC sued 1/2026. 26-O-04 imposed a 6-month pause on special exceptions/conditional-use approvals (lawsuit paused alongside). The moratorium was later partially repealed — it no longer applies west of I-95 or to land zoned Light Industrial/Industrial/Heavy Industrial with the overlay. 9/14/26: council unanimously created a Digital Infrastructure Overlay District (65 dB noise cap, 200 ft buffers, closed-loop or air cooling, 300-acre minimum per development) over 5,000-signature opposition. 10/5/26: settlement with SELC creates a Data Center Exclusion Area across most of the ACE Basin in Colleton. Ordinance numbers for the overlay/exclusion not found.
Earlier InfraWatch research
June–July 2026 research, shown for comparison. Later tracker updates above take precedence.
2026-07: Moratorium adopted — Colleton County Council (6-month, extendable); SELC lawsuit paused
The CSV export does not preserve the original article links. Confirm the underlying record before relying on this lead.
InfraWatch sources and methodology ↗Darlington County
0 project records · 0 local action records
No entry in the supplied tracker. This does not establish that the county has no data centers or local rules.
Dillon County
0 project records · 0 local action records
No entry in the supplied tracker. This does not establish that the county has no data centers or local rules.
Dorchester County
1 project records · 0 local action records
Projects
Google Dorchester County campuses (2 sites)
Under development — groundbreaking Sept. 2024
- Developer / Operator
- Municipality (if any)
- Ridgeville ("Project Dawson," 1055 Research Center Dr., ~230 acres) and St. George (Winding Woods Commerce Park, ~206 acres) — per DatacenterDynamics, 9/27/24
- Capacity / Investment
- $2B for the 2 Dorchester campuses; $3.3B total statewide including the Berkeley County expansion (Governor's Office, ~200 new operational jobs). The earlier "source conflict" was two different scopes, not a disagreement.
- Expected Year / Milestone
- Announced 2024; multi-year buildout
- Permitting & Process Notes
- Site names/acreage come from DatacenterDynamics (9/27/24), which reported Google breaking ground on both campuses; the governor.sc.gov release names the county only. Construction progress since groundbreaking not re-verified.
Earlier InfraWatch research
June–July 2026 research, shown for comparison. Later tracker updates above take precedence.
2025-01: Public-records win — court-ordered disclosure of a data center water demand (Dorchester County)
The CSV export does not preserve the original article links. Confirm the underlying record before relying on this lead.
InfraWatch sources and methodology ↗Edgefield County
0 project records · 0 local action records
No entry in the supplied tracker. This does not establish that the county has no data centers or local rules.
Fairfield County
0 project records · 0 local action records
No entry in the supplied tracker. This does not establish that the county has no data centers or local rules.
Florence County
0 project records · 0 local action records
No entry in the supplied tracker. This does not establish that the county has no data centers or local rules.
Georgetown County
0 project records · 0 local action records
No entry in the supplied tracker. This does not establish that the county has no data centers or local rules.
Greenville County
0 project records · 0 local action records
No entry in the supplied tracker. This does not establish that the county has no data centers or local rules.
Greenwood County
0 project records · 1 local action records
Local action
Municipal rules apply within that town or city, not across the whole county.
Greenwood County
PASSED — 1-year moratorium
- Type
- County
- Ordinance / Action
- Ordinance 2026-25 — 1-year moratorium on data-center development
- Key Date(s)
- 2nd reading 4-3 on 7/7/26; 3rd/final reading 4-3 on Tuesday 7/21/26 (date inferred from 7/24 report)
- Summary
- 12-month moratorium; effective immediately on passage. Voted for: Pruitt, Miller, Allison, Templeton; against: Lane, Griffin, Bishop.
Earlier InfraWatch research
June–July 2026 research, shown for comparison. Later tracker updates above take precedence.
2026-07: 1-year moratorium (4-3) + data centers barred from industrial districts — Greenwood County Council
The CSV export does not preserve the original article links. Confirm the underlying record before relying on this lead.
InfraWatch sources and methodology ↗Hampton County
0 project records · 0 local action records
No entry in the supplied tracker. This does not establish that the county has no data centers or local rules.
Horry County
0 project records · 0 local action records
No entry in the supplied tracker. This does not establish that the county has no data centers or local rules.
Jasper County
0 project records · 0 local action records
No entry in the supplied tracker. This does not establish that the county has no data centers or local rules.
Kershaw County
0 project records · 0 local action records
No entry in the supplied tracker. This does not establish that the county has no data centers or local rules.
Lancaster County
0 project records · 0 local action records
No entry in the supplied tracker. This does not establish that the county has no data centers or local rules.
Laurens County
0 project records · 1 local action records
Local action
Municipal rules apply within that town or city, not across the whole county.
Laurens County
PASSED — 1-year moratorium
- Type
- County
- Ordinance / Action
- 1-year moratorium on data-center projects
- Key Date(s)
- 1st reading unanimous 7/13/26; 2nd reading 8/10/26; public hearing + 3rd/final reading 9/14/26, 6-0
- Summary
- Halts acceptance, review, approval and issuance of permits for data-center development for one year. Planning Commission/council to study zoning, setbacks, noise, water/wastewater, electric infrastructure, traffic, decommissioning; county must review the study by 3/14/27. Council can extend by resolution.
Lee County
0 project records · 0 local action records
No entry in the supplied tracker. This does not establish that the county has no data centers or local rules.
Lexington County
0 project records · 0 local action records
No entry in the supplied tracker. This does not establish that the county has no data centers or local rules.
Marion County
1 project records · 0 local action records
Projects
Stream Data Centers — Project Liberty (CANCELED)
Canceled (announced ~6/10–6/11/26)
- Developer / Operator
- Stream Data Centers
- Municipality (if any)
- Unincorporated
- Capacity / Investment
- $800M first phase (3 buildings of 655,770 sq ft); $2.4B full build-out (up to 9 buildings, ~400 acres, 60 permanent jobs at build-out)
- Expected Year / Milestone
- N/A — canceled
- Permitting & Process Notes
- Stream said utility power "cannot be sourced on this site within the required timeframe." County had approved incentives in January; residents objected that the project wasn't identified as a data center at the time. Stream said it will still distribute funds committed to local organizations (after-school programs, libraries). Earlier tracker date of 6/18 was not supported by sources; first reports are dated 6/11/26.
Marlboro County
0 project records · 0 local action records
No entry in the supplied tracker. This does not establish that the county has no data centers or local rules.
McCormick County
0 project records · 0 local action records
No entry in the supplied tracker. This does not establish that the county has no data centers or local rules.
Earlier InfraWatch research
June–July 2026 research, shown for comparison. Later tracker updates above take precedence.
2026-07: Planning commission sided with residents — recommended denying the rezoning
The CSV export does not preserve the original article links. Confirm the underlying record before relying on this lead.
InfraWatch sources and methodology ↗Newberry County
1 project records · 1 local action records
Projects
Project Altair (DENIED)
Denied (June 2026)
- Developer / Operator
- Undisclosed developer
- Municipality (if any)
- Mid-Carolina Commerce Park
- Capacity / Investment
- Land-sale/site ordinance for potential data center
- Expected Year / Milestone
- N/A — denied
- Permitting & Process Notes
- County Council unanimously denied the land-sale ordinance in June 2026 after resident concerns over water, rates, and rural character; county then finalized a 12-month permit moratorium (confirmed 7/15/26).
Local action
Municipal rules apply within that town or city, not across the whole county.
Newberry County
PASSED
- Type
- County
- Ordinance / Action
- 12-month moratorium on new data-center permits (Project Altair land-sale ordinance denied first)
- Key Date(s)
- Land-sale ordinance denied unanimously 6/3/26 (3rd reading); moratorium (≥12 months) put in effect 6/3/26, confirmed unanimously 7/15/26
- Summary
- Council denied the ordinance that would have allowed sale of county land for Project Altair, then unanimously confirmed a 12-month moratorium on accepting new data-center permits; council may extend it. Cited water, electric-rate, noise, and rural-character concerns.
Earlier InfraWatch research
June–July 2026 research, shown for comparison. Later tracker updates above take precedence.
2026-06: Project rejected + 1-year moratorium — Newberry County Council
The CSV export does not preserve the original article links. Confirm the underlying record before relying on this lead.
InfraWatch sources and methodology ↗Oconee County
0 project records · 0 local action records
No entry in the supplied tracker. This does not establish that the county has no data centers or local rules.
Orangeburg County
0 project records · 0 local action records
No entry in the supplied tracker. This does not establish that the county has no data centers or local rules.
Pickens County
0 project records · 0 local action records
No entry in the supplied tracker. This does not establish that the county has no data centers or local rules.
Richland County
0 project records · 0 local action records
No entry in the supplied tracker. This does not establish that the county has no data centers or local rules.
Saluda County
0 project records · 0 local action records
No entry in the supplied tracker. This does not establish that the county has no data centers or local rules.
Spartanburg County
4 project records · 1 local action record
On November 3, Council advanced three development agreements on second reading. The November 16 tentative agenda lists third and final readings for all three.
November 16 agenda and agreements ↗
Projects
Valara Holdings / NorthMark Strategies — Project MOC-1
Under construction — contested (air permit issued 9/18/26; appealed)
- Developer / Operator
- Valara Holdings / NorthMark Strategies
- Municipality (if any)
- Unincorporated
- Capacity / Investment
- ~$2.76B; ~27 expected (not required) FT jobs; seeking ~450 MW on-site gas generation air permit
- Expected Year / Milestone
- Construction in progress; development agreement scheduled for final reading November 16, 2026.
- Permitting & Process Notes
- SCDES issued the final air permit 9/18/26 (synthetic-minor: federally enforceable limits <10 tpy of any single hazardous air pollutant, <25 tpy combined; formaldehyde recalculated to 10.58 tpy vs 9.39 in the May draft). SELC (for Concerned Citizens of Spartanburg County and Southern Alliance for Clean Energy) filed a contested-case request at the Administrative Law Court on 10/16/26. A judge dismissed SELC's county zoning suit on 10/5/26 for failure to first appeal to the Board of Zoning Appeals; SELC says it will appeal. SELC's PSC siting case (Docket 2026-158-E) is now before the SC Court of Appeals. Spartanburg County's 1-year moratorium (passed 9/21/26, 5-1, facilities >65 MW) does not apply to already-approved projects including Valara. Earlier hearing 6/25/26 was on an expansion from ~50 MW to ~450 MW.
AIB CLT1 LLC — Tyger River Industrial Park
Development agreement advanced November 3; final reading scheduled November 16, 2026
Proposed upgrade to an existing data center site on Tyger River Industrial Drive in Moore.
November 16 agenda and agreements ↗300 Jones Road Associates LLC — Jones Road
Development agreement advanced November 3; final reading scheduled November 16, 2026
Proposed new data center at the former R.R. Donnelley industrial site.
November 16 agenda and agreements ↗TigerDC — Project Spero (WITHDRAWN)
Withdrawn (2/27/26)
- Developer / Operator
- TigerDC
- Municipality (if any)
- Tyger River Industrial Park-North
- Capacity / Investment
- $3B proposed; ~50 FT jobs Phase I
- Expected Year / Milestone
- N/A — withdrawn
- Permitting & Process Notes
- Announced 1/27/26; withdrawn 2/27/26 after local opposition and expected county action against incentives. Developer said it would evaluate alternative sites.
Local action
Municipal rules apply within that town or city, not across the whole county.
Spartanburg County
PASSED — 1-year moratorium (facilities >65 MW)
- Type
- County
- Ordinance / Action
- 1-year data-center moratorium (3rd reading, with 4 amendments)
- Key Date(s)
- 1st reading unanimous 6/22/26 (pending-ordinance doctrine invoked); 3rd/final reading 9/21/26, 5-1 (Coker opposed)
- Summary
- Pauses new data-center development countywide for one year, but only for facilities larger than 65 MW. Not affected: data centers already approved (incl. Valara on S. Pine St.); facilities ≤65 MW in an established industrial park or former industrial site (no self-generation except emergency backup; must primarily store/manage/process data); routine business IT and crypto mining are exempt. Effective date not stated in coverage.
Earlier InfraWatch research
June–July 2026 research, shown for comparison. Later tracker updates above take precedence.
2026-06: 1-year moratorium — first reading (pending-ordinance doctrine) freezes new projects immediately
The CSV export does not preserve the original article links. Confirm the underlying record before relying on this lead.
InfraWatch sources and methodology ↗Sumter County
Local action · Updated November 1, 2026
Standards adopted; moratorium rescission pending
Applies to unincorporated Sumter County.
October 27 council actions
Final standards approval reported. Moratorium not yet lifted.
- OA-26-01: development standards
- South Carolina Record reports third-reading approval on October 27, 2026.
- Ordinance 26-1056: moratorium rescission
- The same meeting report records second-reading approval only. The moratorium remains in effect pending third and final reading.
- Protections to review
- Zoning, water and cooling systems, electricity infrastructure, noise, setbacks, vibration, independent technical review, and enforcement.
- Source status
- The county’s records page lists the October 27 agenda but had not posted minutes when checked November 1. The meeting summary is AI-assisted and is not an official government record. Final adopted text and technical exhibits have not been reviewed; draft distances and limits are not presented here as adopted requirements.
- What residents can do
- Check the county’s next agenda for the final rescission reading and public-comment arrangements. Ask for the adopted standards, supporting studies, and enforceable compliance requirements. No final-reading date is confirmed here.
October 27 meeting summary ↗ · Official agendas and minutes ↗
Union County
1 project records · 1 local action records
Projects
Project Alpaca
Paused at incentive stage
- Developer / Operator
- Undisclosed developer
- Municipality (if any)
- Midway Green Industrial Park
- Capacity / Investment
- 49 MW; $410M fixed-asset investment; 50+ permanent jobs, 500+ construction jobs
- Expected Year / Milestone
- TBD
- Permitting & Process Notes
- County tabled proposed FILOT (4/28/26) and canceled a 5/12/26 public hearing; county says it will hold a public forum if project is reintroduced.
Local action
Municipal rules apply within that town or city, not across the whole county.
Union County
PAUSED (informal) — no ordinance filed
- Type
- County
- Ordinance / Action
- FILOT for Project Alpaca tabled; public hearing canceled
- Key Date(s)
- FILOT 1st reading tabled 4/28/26; hearing canceled ahead of 5/12/26
- Summary
- No moratorium ordinance yet, but council tabled the incentive package that would have advanced Project Alpaca and pulled the scheduled public hearing; says it will hold a public forum if the project returns.
Williamsburg County
0 project records · 0 local action records
No entry in the supplied tracker. This does not establish that the county has no data centers or local rules.
York County
1 project records · 1 local action records
Projects
QTS York County Campus – DC1–DC9 (9 buildings, 3 phases)
Under construction (DC1 topped out 6/30/26); site plans vested
- Developer / Operator
- QTS Realty (Blackstone)
- Municipality (if any)
- Unincorporated (near Lake Wylie / Hands Mill Hwy)
- Capacity / Investment
- $8B projected total; ~1,000 construction jobs, ~200 permanent jobs
- Expected Year / Milestone
- DC1/DC2: 2027; DC5/DC6: 2029; DC9: 2031
- Permitting & Process Notes
- Originally approved 2023 as by-right ("Project Cobra"); all 9 buildings' site plans are vested and EXEMPT from York County's July 2026 moratorium. Council tightened zoning (special exception, acoustical studies, water/power disclosure) in Feb–Mar 2026.
Local action
Municipal rules apply within that town or city, not across the whole county.
York County
PASSED — Zoning tightened + moratorium
- Type
- County
- Ordinance / Action
- Zoning text amendment (2nd reading 3/2026) + 9-month moratorium (final approval 7/13/26)
- Key Date(s)
- Feb–Mar 2026 (zoning); 6/15/26 1st reading, 6/29 2nd, 7/13/26 final (6-0, 9 months)
- Summary
- Moved data centers from by-right to special exception in Light Industrial/Industrial zones; requires acoustical studies, water/power demand disclosure, setbacks, screening, closed-loop cooling. Moratorium (effective immediately) pauses new special exceptions/conditional-use site plans; QTS's 9 existing buildings are exempt (vested rights).